IMPORTANT NOTICE: Please be advised that pursuant to Cupertino Municipal Code 2.08.100 written communications sent to the Cupertino City Council, Commissioners or City staff concerning a matter on the agenda are included as supplemental material to the agendized item. These written communications are accessible to the public through the City's website and kept in packet archives. You are hereby admonished not to include any personal or private information in written communications to the City that you do not wish to make public; doing so shall constitute a waiver of any privacy rights you may have on the information provided to the City.

File #: 21-9095    Version: 1 Name:
Type: Ordinances and Action Items Status: Approved as Amended
File created: 4/1/2021 In control: City Council
On agenda: 6/1/2021 Final action: 6/1/2021
Title: Subject: Consideration of 1) Authorization of Award of Construction Contract for Privacy Fencing; 2) Request to Increase Regnart Creek Trail Privacy Fencing Project Budget Allocation; 3) Request to Increase Budget Allocation for Regnart Creek Trail Project Contingency; 4) Request to Increase Budget Allocation for Regnart Creek Trail and Regnart Creek Fencing Design Services; and 5) Request to Execute a First Amendment to the Master Agreement Between the City and CSG Consultants, Incorporated to Increase Agreement Amount.
Attachments: 1. Staff Report, 2. A - Draft Contract

Title

SubjectConsideration of 1) Authorization of Award of Construction Contract for Privacy Fencing; 2) Request to Increase Regnart Creek Trail Privacy Fencing Project Budget Allocation; 3) Request to Increase Budget Allocation for Regnart Creek Trail Project Contingency; 4) Request to Increase Budget Allocation for Regnart Creek Trail and Regnart Creek Fencing Design Services; and 5) Request to Execute a First Amendment to the Master Agreement Between the City and CSG Consultants, Incorporated to Increase Agreement Amount.

 

Recommended Action

Recommend that the City Council:

1.                     Authorize the City Manager to Award a Construction Contract with California Commercial Fence Company in an Amount not to exceed $1,504,069, and Authorize the Director of Public Works to Execute any Necessary Change Orders, up to the Construction Contingency Amount of $300,814, for a Total Authorized Contract Amount of $1,804,883, for the Regnart Creek Fencing Project;

2.                     Approve Budget Modification #2021-143 increasing appropriations in the Capital Improvement Program Capital Projects Fund (420-99-036) by $1,159,883 for the Regnart Creek Trail Fencing Project;

3.                     Approve Budget Modification #2021-143 increasing appropriations in the Capital Improvement Program Capital Projects Fund (420-99-036) by $175,000 for Regnart Creek Trail Project Contingency;

4.                     Approve Budget Modification #2021-143 increasing appropriations in the Capital Improvement Program Capital Projects Fund (420-99-036) by $25,000 for Regnart Creek Trail and $30,000 for Regnart Creek Trail Fencing Project for additional design services; and

5.                     Authorize the City Manager to Execute a First Amendment to Agreement 2021-11, a Master Agreement between the City of Cupertino and CSG Consultants, Incorporated, to increase agreement amount from $500,000 to $538,045.