Title: Subject: Award a construction contract for 2024 Pavement Maintenance Phase 1 Project to G. Bortolotto & Co. for asphalt mill & fill and patching on identified roadways throughout the City of Cupertino in the amount of $2,662,786.
Attachments: 1. Staff Report, 2. A - Draft Contract, 3. B - Location List, 4. C - Location Map

Title

Subject:  Award a construction contract for 2024 Pavement Maintenance Phase 1 Project to G. Bortolotto & Co. for asphalt mill & fill and patching on identified roadways throughout the City of Cupertino in the amount of $2,662,786.

 

Recommended Action

1. Award a construction contract for the 2024 Pavement Maintenance Phase 1 project (project number 2024-101) in the amount of $2,662,786 to G. Bortolotto & Co.

2. Authorize the City Manager to execute the construction contract when all conditions have been met; and

3. Authorize the Director of Public Works to execute any necessary change orders up to a construction contingency amount of $266,279 (10%) for a total contract amount of $2,929,065.