Legislation Details

File #: 18-4159    Version: 1 Name:
Type: Consent Calendar Status: Approved
File created: 7/9/2018 In control: City Council
On agenda: 8/21/2018 Final action: 8/21/2018
Title: Subject: 2018 Pavement Maintenance Phase 2 Project, Project No. 2019-102
Attachments: 1. Staff Report, 2. A - List of Streets to Receive Pavement Maintenance Treatment, 3. B - Draft Contract

Title

Subject2018 Pavement Maintenance Phase 2 Project, Project No. 2019-102

 

Recommended Action

Authorize the City Manager to award a contract to Graham Contractors, Inc., in the amount of $290,769 and approve a construction contingency of $29,000, for a total of $319,769