Subject: Contract amendments for professional building department and public inspection services for Apple Campus 2
Recommended Action
Staff recommends that the City Council:
1. Authorize the City Manager to:
a. Execute the Third Amendment to Agreement 14-028 with 4LEAF, Inc. for Apple Campus 2 Phase 1 building inspection services and public works inspection services to increase the previously authorized contract amount by $1,829,890 for a total amount not to exceed $16,956,368; and
b. Execute the Second Amendment to Agreement 15-146 with 4LEAF, Inc. for Apple Campus 2 Phase 2 building inspection services to increase the previously authorized contract amount by $524,068 for a total amount not to exceed $1,438,855
2. Authorize the City Manager to execute contract amendments to the extent that the costs are recovered from the project applicant
3. Approve the budget allocations necessary to execute the contract amendments