IMPORTANT NOTICE: Please be advised that pursuant to Cupertino Municipal Code 2.08.100 written communications sent to the Cupertino City Council, Commissioners or City staff concerning a matter on the agenda are included as supplemental material to the agendized item. These written communications are accessible to the public through the City's website and kept in packet archives. You are hereby admonished not to include any personal or private information in written communications to the City that you do not wish to make public; doing so shall constitute a waiver of any privacy rights you may have on the information provided to the City.

File #: 23-12477    Version: 1 Name:
Type: Consent Calendar Status: Agenda Ready
File created: 7/14/2023 In control: City Council
On agenda: 6/4/2024 Final action:
Title: Subject: Construction contract and a proposed amendment to the design consultant agreement and construction management services for the All-Inclusive Playground at Jollyman Park project
Attachments: 1. Staff Report, 2. A - Draft Contract - QLM, Inc., 3. B - DRAFT Agreement Amendment - MIG, Inc., 4. C - DRAFT Agreement - 4Leaf, Inc., 5. D - Draft Resolution

Title

SubjectConstruction contract and a proposed amendment to the design consultant agreement and construction management services for the All-Inclusive Playground at Jollyman Park project

 

Recommended Action

1.                     Award a construction contract for the All-Inclusive Playground at Jollyman Park Project (budget unit 420-99-051) in the amount of $3,863,430 to QLM, Inc.;

2.                     Authorize the City Manager to execute the contract with QLM, Inc. when all conditions have been met;

3.                     Authorize the Director of Public Works to execute any necessary construction change orders with QLM, Inc., up to a contingency amount of $386,350 (10%), for a total contract amount of $4,249,780;

4.                     Authorize the City Manager to execute an amendment to the agreement with MIG, Inc. for Design Professional Services on the All-Inclusive Playground at Jollyman Park project (420-99-051, PO# 2022-0326) increasing the contract amount by $45,000, for a new total not-to-exceed contract amount of $467,411;

5.                     Authorize the City Manager to execute a professional services agreement with 4Leaf, Inc. for construction management services for a total not-to-exceed contract amount of $393,081; and

6.                     Adopt Resolution No. 24-049 approving budget modification #2324-304, approving a transfer out of $500,000 from the Park Dedication Fund (280) and a transfer into the All-Inclusive Playground at Jollyman Park Project (budget unit 420-99-051) and appropriating $500,000 to this project.